Spring 2019 Construction Update

Numerous improvements to our campus buildings and roadways are underway or wererecently completed. Here is a brief update on recent and current construction projects.

Middle Tennessee Boulevard

  • Working on Alma Mater Drive circle
  • Finishing entrance columns andpavers at Faulkinberry Drive
  • Constructing curbs and gutters inmedian, top soil, and installingirrigation lines
  • Completing Bell Street entrance plaza•Anticipating final asphalt toppingthis spring
  • Scope of work:

»$15.7 million project»Widening of 0.8-mile section ofMiddle Tennessee Boulevardbetween East Main and Greenlandto a divided four-lane street

»Landscaped median withdedicated turn lanes»Improved pedestrian walksand crossings

»Bike lanes

»Improved lighting

»New underground utilities

»Monument entry walls toMTSU campus

»New drop-off at Murphy Center»Improvements to the FaulkinberryDrive intersection

Parking Services Facility

  • Design development phase completed
  • Construction starting late spring andfinishing in summer 2020
  • Scope of work:

»New home for Parking Services,including parking permits, busmaintenance, and personnel offices

»Located on City View Drive

»$3.4 million project budget

»13,000-square-foot building area

Academic Classroom Building

  • MTSU College of Behavioral and Health Sciences Academic Building RenderingNew center for the College ofBehavioral and Health Sciences
  • Consolidating the Criminal JusticeAdministration, Psychology, andSocial Work departments
  • Providing critically neededclassrooms, offices, and lab spaces•Sitework construction (site utilitiesand grading) wrapping up in January
  • Building construction startingin January
  • Project completion expectedsummer 2020
  • Scope of work:

»$39.6 million total project cost»State funding received last July 13

»91,000 square feet

»Building site north of the StudentUnion across MTSU Boulevard

»Construction manager generalcontractor: Turner Construction Co.

»Architect: Bauer Askew Architecture

Peck Hall

  • Interior improvements completed
  • “Energetic” courtyard that’s beencreated by new exterior furniture
  • Scope of work:

»$924,000 construction cost

»Interior improvements, includingnew lighting at corridors andrefinishing of terrazzo flooringon second and third levels

»New ceiling and lightingat breezeways

»New outdoor furnishings

Parking and TransportationImprovements

  • New sidewalks open to studentsreturning to class in January
  • Scope of work:

»$1.58 million construction cost»New surface and lighting atGreenland Drive parking lot

»New sidewalks and lighting alongAlumni Drive and MilitaryMemorial Drive

»Improved pedestrian access toLivestock Lot and new lighting

»Wider sidewalks along FoundersLane

»Small roundabout at MilitaryMemorial and Champion Way